  74   02 Nov 2022, 14:40 Orkidia BilaniXHEXPInformationSQS support

Discussed by the end of September with T.Mullins and D. Rivas, to remove the laser tables from the exp.hall area, in case they won't be needed anymore.

Today we supported SQS in dismountig and removing these tables (1*2 m²) from the exp.hall.

Coworkers: O.Bilani, S. Menzel, D. Rivas, J. Monotano

  535   24 Jan 2024, 13:37 Frank SiyliXHEXPInformationSQS support

Nils Rennhack unterstützt.

Leitungssätze im Podest entfernt und neu verlegt.

Coworker: Nils Rennhack, Sascha Menzel, Orkidia Bilani, Frank Siyli

  118   16 Dec 2022, 11:51 Michael LuedekeGeneralInformationSQS start installation frame for exhaust
  1051   18 Feb 2025, 10:34 Benjamin WolfGeneralInformationSQS Transport

Die Kammer #48500 aus XHE 1 in die Halle transportiert

 

 

coworkers:O. Bilani, K. Pfeiffer, B. Wolf

  139   11 Jan 2023, 17:58 Orkidia BilaniXHEXPInformationSQS Support: 19-20.01.2023

SQS requested the following support  from XHCrew:


Thursday and Friday of next week SQS expect to carry on some installation works in their hutch with expected activities:

- To make modifications to an existing frame
- To assemble a new frame
- Support with craning into the hutch of COMO source

 

  409   22 Sep 2023, 10:47 Orkidia BilaniXHEXPInformationSQS Support in XHEXP1

SQS doesn't have many space left in their assembly area. Talked/dealed with the SQS colleagues, and managed to free spaces :-).

The parts/components will be transported to XHE1 and to Ütersen.

Sascha will do the transport to XHE1 on his shift over the weekend. The transport to Ütersen will be done next week.

 

Coworkers: O.Bilani, N. Rennhack, J. Montano, A. Igharas, S. Menzel, S. Dold

 

  573   27 Feb 2024, 15:43 Orkidia BilaniXHEXPInformationSQS Support in XHE1

Suppoerted SQS in XHE1 with disassembling parts from the cluster source and transported these components back to XHEXP1.

Co-workers: Y. Ovcharenko, A. Igharas, O. Bilani

  381   23 Aug 2023, 13:29 Sascha MenzelXHEXPInformationSQS Support am 22.08.2023

Bei SASE3 die Seitenwände vom Laserraum zwischen SASE3 und SASE1 demontiert (geöffnet) dann zwei Schubladenschränke mit dem Hubwagen weg transportiert. Diverse Leitungen und Kühlwasserschläuche demontiert und die drei Lasertische mittels mobielen Kran aus dem Laserraum gekrant und auf Transportrollen gestellt. Die Lasertische zur SQS Area transportiert und mittels Hallenkran in Holzkisten gekrant. Die Holzkisten hatte zuvor O.Smith in die Halle transportiert. Einen Chiller aus dem Laserraum von der Wasserversorgung getrennt und aus dem Raum transportiert. Zum Schluss die Wandelemente wieder montiert und die Wand somit geschlossen.

Coworkers: S.Menzel, N.Rennhack, D.Raiser, A.Igharas und T.Mullins

  456   01 Nov 2023, 11:07 Orkidia BilaniXHEXPInformationSQS Support

Discussed with T.Mazza on Monday, 30.10.2023, about storing temporarily in XHE1 the wooden boxes of an equipment they recevied recently. 

They should be stored until the equipment is tested and working, so that if something goes wrong, it can be shipped to the manufacturer with the original Verpackung 

If all fine, they will be disposed, most probably by the end of winter maintenance period.

 

Transport was done!

Co-workers: S.Menzel. O.Bilani, J. Montano

  480   28 Nov 2023, 19:33 Orkidia BilaniXHEXPInformationSQS Support

Supported SQS with carrying the top small cabinets and placing them on the bigger ones.

Co-workers: O. Bilani,  M. Peter, A. Igharas, J. Montano

  481   29 Nov 2023, 19:46 Orkidia BilaniXHEXPInformationSQS Support

Brought Back from XHE1 into the Experiment Hall the "PAM - Chambers".

Co-workers: O. Bilani, H. Heuer

 

  760   07 Aug 2024, 21:00 Orkidia BilaniXHEXPInformationSQS Support

Dismounted a R+K "Gestell" of SQS. Brought the R+K to the Warehouse. 

The wheels are still in the Exp.Hall, because maybe Sascha and Paul would need them soon.

  23   22 Sep 2022, 19:44 Orkidia BilaniXHEXPInformationSQS Support

SQS support:

-> Completed the building up of the vacuum pump and mounted it in the beamline (pic.a and b).

-> Craned and mounted (attached) the 1D XUV spectrometer (from Uppsala) into the beamline (pic.c and d).

 

Coworkers: O,Bilani, Th. Baumann, J. Montano

 

  24   26 Sep 2022, 15:23 Sascha MenzelXHEXPInformationSQS Support

Granitsteine (wo der 1D XUV spectrometer drauf steht) mittels Hutch-Kran versetzt.

Coworkers: Th.Baumann, O.Bilani, M.Lüdeke, S.Menzel

  48   04 Oct 2022, 12:30 Sascha MenzelXHEXPInformationSQS Support

XHCrew hat an das Reinraumzelt in der SQS Hutch eine Lochwand montiert.

 

Coworkers: M.Lüdeke, S.Menzel

  171   07 Feb 2023, 13:10 Sascha MenzelGeneralInformationSQS Support

Für N.Rennhack (SQS) zwei Ausschnitte in einen Schaltschrank mit einer Stichsäge ausgeschnitten.

 

Coworkers: S.Menzel, M.Lüdeke 

  236   24 Mar 2023, 15:49 Sascha MenzelGeneralInformationSQS Support

Im SQS Labor E0.508 am Aufbau für die Hochdruckpumpen die Kühlwasserleitungen durch Schläuche ersetzt.

Coworkers: M.Togawa, S.Menzel

  240   25 Mar 2023, 20:23 Sascha MenzelGeneralInformationSQS Support

Einen Halter zum befestigen von Schnellkupplung für Kühlwasserschläuche konstruiert und zusammen gebaut. Den Halter mit den Schnellkupplungen an das Gestell montiert.

  262   05 Apr 2023, 18:14 Orkidia BilaniXHEXPInformationSQS Support

Went with Yevheniy and Sergei to XHE1. They dismount and took some controllers and cables from the COMO setup.

  268   18 Apr 2023, 19:02 Sascha MenzelXHEXPInformationSQS Support

Für SQS eine Kammer mittels Hallenkran auf ein Gestell gekrant.

 