-> FXE: mentioned, as two days ago, that they will need support on 10.10 for craning of the Kappa Goniometer: Hall Crew will try to find the best solution for that and organize a meeting between FXE, HallCrew and S. Arslan.
They asked if we know when can they have He again, but we made it clear that XHCrwe doesn't have any news about that and we are not the point of contact for gases.
-> SXP: support on finishing the building up of the Frame for the Momentum Microscope (Tuesday 4.10.2022). V. Vardanyan was aksed to start mounting early in the morning and HallCrew will join for support at 10:00 am.
needs support on craning a pump (details on what and when exactly will follow).
-> PLA: must/have to drill few holes for the central pressurized air into the pillars (Säule) in the exp.hall. Since they must drill only on mondays (when there is no beam and the measurements do not get disturbed from vibrations) and 3.10 is a holyday, they asked for permission to drill on Tuesday (4.10), but not the entire day.
FXE. HED, SQS and SCS do not see a problem on that. Other Instruments still to be asked.
-> The instruments' representative were informed that from 10.10 - 15.10 only M. Lüdeke is present from XHCrew and the week after, 17.10 - 21.10 no member of XHCrew is there due to vacation/training. O.Bilani will check anyway regularly the emails and will be telefonisch erreichbar in any case and reminded the colleagues to keep the hall free from any chaos, danger and waste.
|