Group Selection Page
HELP
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Operation
PSPO
XO
TS
Migrated2Zulip
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 475
Entry time: 06 Dec 2023, 09:49
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 06.12.2023 |
|
|
General Announcement:
- Jan Gruenert announces a seminar done by UK guests from Daresbury on UK plans for FEL. The seminar happens on THU 13:30 at XHQ E2.042. Please contact Jan G. for zoom link.
CTRL:
- Few hiccups when performing Monday's update was done: restarted system again and fixed now.
- HED had also an issue with router but was understood and fixed.
- Performed SA1 update and today continuing with SA2 and tomorrow SA3 topics.
DA:
- Nothing to report.
EEE:
- Doing updates in SA1 tunnel PLC updates today.
- Affected by personal missing due to sickness.
VAC:
- Maintenance activities are ongoing.
XPD:
- Tasks progressing as scheduled.
DET:
- Nothing to report.
ITDM:
- Routers update were done on Monday and Tuesday. They are operational and connected - looks successful.
- HED problem with a faulty connection/switch but for the time been it shall be fine.
XRO:
- Nothing to report.
LAS:
- Issue after Karabo update: can not instantiate and restart system; CTRL received a ticket and is looking into it.
UNSYS:
- Fixed problem with broken encoders in tunnels; calibration of cam movers was successful and is ready to install Apple-X; broken connector was found but reason for this happen still under investigation.
- First 2 Apple-X will be installed Thursday.
- Next 2 Apple-X to be moved to shaft building on Friday and installed on Monday.
SPB:
- Issue after power maintenance last week: downstream control room and experimental hutch does not have power in some white/orange sockets; A ticket to TS was written.
FXE:
- Nothing to report.
- Electronics rack room were switched ON now.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Not present. |