Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 472     Entry time: 27 Nov 2023, 09:39
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 27.11.2023 
General Announcement:
- User operation finished this morning 7AM for the year.
- Reminder that WMP starts on Thursday. Possible photon tunnels open on Wednesday but this still to be confirmed and e-mail will be sent.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.
DET:
- AGIPD at MID: issue on weekend with the bias motion. The power system for high voltage was changed but it did not cure the system. 
Further investigation with the modules will happen during the WMP. MID managed to finish the beamtime.

ITDM: 
- GPFS issue reported by DRC on Friday: happened only one time and did not repeat.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Remind SA3 and SA2 problems (needs ZZ): BKR will continue working and during the WMP it will be fixed.

SPB:
- Pointing/jitter issue reported by Adam R. on E-log: Romain Letrun reports that is was a drift but not much different from usual behavior and not a real problem.

FXE:
- Nothing to report.

MID:
- Could run 2 AGIPD modules during the weekend.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.