Entry time: 01 Nov 2023, 10:04
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 01.11.2023 |
|
|
General Announcement:
- Jan G. as PRC comments: 1. reminds SQS and FXE instruments to place entries at the Operations e-log;
2. machine is running well and ZZ accesses happened on Monday (hindered by issues with tunnel entrance) but all done;
3. the XTD2 issue with upstream differential pump close to the XGM: one pump is defective and VAC will exchange if a ZZ is allowed next week.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- FSSS motor in MID: OCD received a call yesterday and device was restarted and came back to operation.
VAC:
- Not present.
XPD:
- Nothing to report from XPD.
DET:
- Nothing to be reported.
ITDM:
- Nothing to report.
XRO:
- On the XTD10 ZZ last Monday: V-slit was checked and a faulty cable for the encoder was found. For the time being this was fixed by tapping it and will continue monitoring.
LAS:
- Nothing to report.
UNSYS:
- All fine with Undulator.
SPB:
- Nothing to report.
FXE:
- Beam was not stable the last night / down for few times. To be investigated internally at FXE and reported to XO.
MID:
- Roll motor for M2 mirror at tunnel was moving very slowly; to be seen with XRO.
HED:
- Nothing to report.
SCS:
- Nothing to report; working in hutch preparations.
SQS:
- Nothing to report.
SXP:
- Not present. |