Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 446
Entry time: 23 Aug 2023, 09:47
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 23.08.2023 |
|
|
General Announcement:
- Next Monday, 28.08 there is no XO Integration Meeting due to agenda unavailability of XO.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Not present.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Tri way valve SA2 cell4 causing warm water in vacuum chamber which drifts the gap for few um. To be fixed in a shutdown.
- Cell25/SA2 feedback of temperature sensors is solved.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Waiting for beam. Tuning under way.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |