Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 413
Entry time: 24 Apr 2023, 09:53
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 24.04.2022 |
|
|
General Announcement:
- Two cryo events happened last week: one Friday morning 03:30AM and one on Saturday evening. Machine has fully recovered by now. First event was caused by a ceramic bearing of the cold compressor.
- Power glitches were reported at Desy last few days but it seems that no equipment was impacted at XFEL. In case you see differently, please contact XO and TS.
- Next Friday 28.04 it is the deadline for submitting the summer maintenance task list.
CTRL:
- DOC shift was in place until this morning to help from recovery of the cryo events.
DA:
- Quiet week for OCD.
EEE:
- Issues that appeared are being followed by EEE.
VAC:
- All fine with VAC.
XPD:
- No issues with XPD.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- SA2 PP-laser was back running and fine.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Joerg H. will get in touch with XRO / Maurizio V. on a beam clipping issue (originated at the end of MID branch).
- HXRSS was recovered fast during last week.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |