SASE1 Status and SASE3 Readiness Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 398     Entry time: 27 Feb 2023, 09:48
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 27.02.2023 
General Announcement:

- Tobias Clever announces work in safety light installations at XHEXP1 taking place today: no disturbances shall happen and therefore no need to be alarmed.

- As PRC M. Vannoni says operation was smooth (no changes of parameters to keep machine stable).



CTRL:

- Nothing to report.



DA:

- No incidents for OCD: all fine.



EEE:

- MID called OCD for 1. Hexapods (to be followed); 2. Configurations on motors that were fixed.



VAC:

- Nothing to report.



XPD:

- Not present.



DET:

- DSSC is back online at SCS - thanks to involved groups to make it happen. Spare chiller is installed and being in use. Old one needs to be repaired.



ITDM: 

- Nothing special to report.



XRO:

- Nothing to report.



LAS:

- Installing device in SQS PP-laser side.



UNSYS:

- Everything is fine.

- Pb shield for motors are expected to be delivered this week.



SPB:

- Nothing to report.



FXE:

- X-ray delivery worked well.

- Sudden shift of photon energy by 9eV and recalibration was required costing 1 hours.

- Friday night error for undulator gaps costing 50% of intensity. <-- PhaseShifter hysteresis

- Motors moving to wrong positions. CTRL will follow.



MID:

- Problems with encoders in motors which were solved by DOC or followed up.



HED:

- Nothing to report.



SCS:

- Nothing to report.



SQS:

- Nothing to report. Last week of delivery was fine.



SXP:

- Not present.