Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 34
Entry time: 17 Apr 2019, 11:34
|
Author: |
Adriano Violante |
Location: |
General |
Severity: |
Information |
Subject: |
Minutes of the Technical integration meeting 17.04.19 |
|
|
SPB/SFX
- CRL motors being tested. Today BB (AE) will check the status.
- CSS interlock tests being planned for tomorrow.
- Jungfrau motors - SS (EET) fixed some cable issues. Now ok.
- Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET working on it.
- AE needs to know when Loop 9 is expected to run. SPB to check.
FXE
- AE needs to get information on PLCs loop splitting. FXE to comment.
SQS
- Loop 9 will be updated.
- AE helping for commissioning
- AE needs priorities for the next loops. SQS to comment.
SCS
- DSSC installation progressing. Loop 5 motion loops should run
- In general loops have been updated. Loop 13 (part of it) being commissioned. AE needs to know then the entire loop commissionig will start.
- Discussion with EET ongoing concerning the installation of cables for end stations. Space problem.
- Loop 4. BKF536 and 531 being modified. Clarification with AE/EET needed.
MID
- Epix voltage interlocks definition and implementation. AE (MS) and CAS (CY) working on it.
- For Loop 9 CY is preparing a change request. AE involved.
- Loop 12 will be operable this week
- Priorities for next loops needed by AE to plan the work.
HED
- Mono in XTD6 has been fixed.
- Jungfrau and epix commissioned
- Loop 7 being commissioned
- Loops 1, 2 , 5, 7 could be done
- Loop9 (Smaract stages) has to be brough up.
- Loop10 and 11 will be needed in June. HED to confirm.
OPT Lasers
- SA2 PPL work ongoing this and next week. ready by next week.
- AE support is needed in order to bring the SCS laser up by the end of may. Mail has been sent. NJardon checks.
XRO
XPD
- Loop updates procedure being finalized by AE. NK asked for MOV2 loop update during next week. AE will try to follow this up.
- Issue repoeted from CAS: Fast ADC for MCP in SASE3 duplicates data in the 3 % of cases. DAQ is not responsible. Tests have to be made and for that the ADC servers have to undergo to short interruptions. Will be coordinated with XPD. Should not be e problem. CAS to follow the issue up.
VAC
DET
AE
ITDM
EET
CAS
- 5Hz test follow up is being done by CAS. Especially optimization concerning train id and time stamp with DESY with the goal to make the switch between the different operation mode easier. A meeting will be planned.
- 2,4,1. hotfix (Fast data pipeline) is being prepared
SRP
- Oil cans in and outside SPB rackroom should be removed. A proper cabinet has been requested to TS but it is not yet ready since exhaust lines are needed.
- Patch cables in the racks should be limited to the very necessary amount since there the material storage is not allowed . TS can help finding space for this material in the hall..
- Schedule changes for the Summer shutdown due to modification of the interlock systems. Additional meetings needed. No info is expected before the beginning of May.
TS
- Support for chillers. Contact people by TS are T. Bartsch and P. Schmidt. They can support concerning issues and problems with chillers for the day to day operation. LKersting supports that. For bigger project, a specific request should be made to LK.
AoB |