General Announcement: - The cold compressor (stage 2) failed yesterday shortly after lunch time and beam delivery had been cancelled on the remaining of Sunday 12.06. For this week, the delivery is not expected to start prior Tuesday 15:00. Later today PRC or XO will know more on the machine status and will inform instruments. CTRL: - Nothing to report. DA: - Nothing to report. EEE: - Nothing to report. VAC: - Nothing to report. XPD: - Nothing to report. - The issue with SA1 XGM last week was due to a short communication interruption. No need for further action. DET: - Nothing to report. ITDM: - Nothing to report. XRO: - Agreed with MID to recheck beamline alignment (change stripe from Platinum to B4C): has to be communicated when beam is available. LAS: - Nothing to report. UNSYS: - All fine with undulators. SPB: - Nothing to report. - Second user still managed to achieve the goal of the experiment apart of the beamtime lost. FXE: - Nothing to report. MID: - All fine at MID. HED: - Nothing to report; Second user schedule for the weekend was affected. SCS: - Users were struggling with samples at different temperatures. A second sample not achieve much as it was exchanged for Sunday. SQS: - Nothing to report.