Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 323     Entry time: 09 May 2022, 10:30
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 09.05.2022 
General Announcement:
- This week is a Facility development week: photon studies take place until Wednesday and then setup for 16.3GeV for the next weeks of operation.
- Martin Doering present a Dashboard for the Summer maintenance period. About 600 activities were submitted timely by the groups; currently the lists are being processed for checking for major error. 
- Jan G. adds as PRC that there were no major issues during the weekend. The FXE XGMd gave wrong values and is under investigation.

CTRL:
- Few devices are saved in the projects with wrong classID: A script is to be applied today at 13:00 to fix this configuration; it is transparent.
- Update of data logger to be done today at 13:00 (15min downtime) also to improve Influx.

DA:
- No announcements; past OCD was quiet.

EEE:
- This week: intervention to be done in SA3 to allow better slits movement (together with XRO).

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing major to report.

ITDM: 
- Nothing to report.

XRO:
- XRO will be busy next days with beamtime / FDs activities.

LAS:
- A water leak is found in SA1 laser hutch. TS is contacted and the suspicion lies in the humidifier from the roof. There is no estimative on time for repair.
- Maintenance works in SA3 PP-laser to be done until Wednesday.

UNSYS:
- Control system of Apple-X shows several encoders giving errors in several motors. Encoders were failing to start.

SPB:
- Experiments went well last week.

FXE:
- FXE has planned for PP-laser use.
- Martin K. asks if a ZZ for the Mono is happening today. A. Galler inform hat today there is ZZ and therefore the access request is not yet scheduled.

MID:
- MID colleagues still look for a picoampere meter.

HED:
- The Full train test is scheduled to take place today.

SCS:
- Not present.

SQS:
- Nothing to report.