Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 321     Entry time: 02 May 2022, 07:27
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 02.05.2022 
General Announcement:
- Martin Doering gives update on the maintenance planning progress: a Dashboard will be introduced and updated every week and almost all groups have submitted the lists. 	 

CTRL:
- Reminder: today at 13:00 there is a deployment of Karabo Beckhoff in the tunnels (motors with newly features). No issues are expected; otherwise a reset may suffice.

DA:
- Nothing to report.

EEE:
- Nothing to report.
	
VAC:
- Nothing to report.

XPD:
- No incidents to report; 
- Two ZZs in tunnels are taking place this morning.

DET:
- Feedback regarding AGIPD at SPB (cw16): one module has to be replaced during the summer maintenance period. Reason behind the damage has to be investigated together with SPB staff.

ITDM: 
- Nothing to report. 

XRO:
- Nothing to report. 

LAS:
- Nothing to report.
	
UNSYS:
- ZZ taking place at SA3 cell 14 this morning.

SPB:
- Everything went smooth last week.

FXE:
- Couple of issues with Bassler cameras not connecting or acquiring data (DOC helped).
- Gun trips on the weekend means that one hour is needed to wait until running again Mono (using high heat load). Many gun trips were seen during the weekend.
Raul V. says that a possibility was discussed yesterday at around 09:45AM for an intervention to minimize the gun trips but after consultation with FXE staff it was decided to run in that condition. Peter 
Z. says that calling 9-4800 was not reachable.

MID:
- Everything looks good for the last experiment with HXRSS.
- It lost the timing after a big trip on Sunday. 
- Frequent broker Pile-ups happened and for mid-term has to be addressed (J. Hallmann). Gabrielle G. and Setffen H. say that a fix is known and in the mid-term it will be solved. 
- Problem with multipatern of Laser happened; reported by Angel R.-F. LAS will look into it.
	
HED:
- CRL3 was tested and enabled it back.
- Tomorrow the mirror vertical motors will be checked together with XRO.

SCS:
- Nothing to report. Only smaller issues that were addressed.

SQS:
- Nothing to report.
ELOG V3.1.4-7c3fd00