SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 318
Entry time: 20 Apr 2022, 10:07
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 20.04.2022 |
|
|
General Announcement:
- Steffen H. reminds on the Karabo developer training that will take place next week. Registrations are still possible.
- Martin Doering informs that next week Friday 29.04 is the deadline for submitting the summer maintenance lists. In case of needed help, please contact xo-planning@xfel.eu.
CTRL:
- Issue with Influx issue in cw14: data logging is now protected and a Karabo update in only the data loggers machines has to be done.
It is proposed to make it today at 13:00 (it is transparent for the users and takes about 30mins). An e-mail will be sent to the xo-info@xfel.eu.
- Beckoff updates in software level to be performed on next Monday 25.04 at 13:00. This affects mainly tunnels; with instruments the coordination will be done.
DA:
- Nothing to report.
EEE:
- Minor things being supported but nothing major to report.
VAC:
- Nothing to report.
XPD:
- A. Koch asks on the Beckhoff update: only hardware in tunnels will be updated and only Karabo software.
- J. Laksman says that during the Eastern beamtime at SQS a gas needle opened very fast and the pressure of chamber went very fast, posing a damage risk.
A Redmine ticket was placed for that it does not open too fast. An offline discussion will take place with EEE and CTRL.
DET:
- DSSC is back online at SCS after months of non-operation. There are issues to be fixed and investigations are in progress. The DSSC expert is on OCD this week and DOC can also help.
ITDM:
- Nothing to report.
- Marcin S. asks on the plan for limiting the raw data process per run in this current beamtime. SPB staff was told that they can't have more than 10 processes running;
K. Wrona informed this was talked to users and it was agreed with the limited number of 10. An offline discussion will take place and if more is needed this can be accommodated.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- See Marcin S. question above. Nothing else.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Under operation and issue with DSSC was already mentioned.
SQS:
- Not present. |