197
|
02 May 2017, 20:11 |
Jan Grünert | XTD2 | Problem | XGM scenes/devices offline - UHV pressures increasing - Please respond now !! | All devices went into unknown state in
the karabo XGM scenes in XTD2 and XTD9 at
19h52. |
|
196
|
02 May 2017, 15:30 |
Adriano Violante | General | Information | Access to XTDs on Thursday | This Thursday the XTDs will be accessible
with ZZ procedure. Access can be requested
via T. Haas. |
|
195
|
02 May 2017, 10:56 |
Harald Sinn | XTD9 | Information | Status of Vacuum System | XTD2: All gate valves are now OK (not interlocked)
after re-instantiating and re-setting the
XGM_DP_OK. |
|
194
|
02 May 2017, 10:05 |
Tobias Freyermuth | XTD9 | Information | PBLM Motor drivers in PreOP | Hi all,
due to ongoing tests with the PBLM |
|
193
|
29 Apr 2017, 10:04 |
Hugo Silva Santos | General | Information | ERRATA: CAS - On-Call Duty Planning - Valerii, Gabriele and Wajid | Dear All,
Still in time, I would like to correct
out schedule. |
|
192
|
28 Apr 2017, 16:29 |
Janni Eidam | General | Information | Vacuum group call service | Not really official, but in emergency case
you can call 96993 for vacuum group. Next
week Martin is back and I think we will have |
|
191
|
28 Apr 2017, 15:44 |
Jan Grünert | General | Information | WP74 OCD contacts for the coming weekend | WP74 OCD for the coming
weekend 29.4.-1.5.2017:
|
|
190
|
28 Apr 2017, 14:43 |
Hugo Silva Santos | General | Information | CAS - On-Call Duty Planning - Valerii, Gabriele and Wajid | Dear All,
I would like to share the CAS members
on the OCD from 29/04 to 01/05: |
|
189
|
28 Apr 2017, 14:31 |
Tobias Freyermuth | General | Information | AE OCD April 29 - Mai 1 | AE on call service:
Contact person:
|
|
188
|
28 Apr 2017, 13:24 |
Tobias Haas | General | Information | Small correction to minutes posted just before | Note that plans for next week (points 2&
3) should refer to XTD9 and *NOT* XTD2
|
|
187
|
28 Apr 2017, 13:08 |
Tobias Haas | General | Information | Status and plans after SASE1 Readiness Meeting | Tunnel Status (T. Haas):
Tunnels XTD2/4/10 were
interlocked yesterday afternoon
|
|
186
|
28 Apr 2017, 08:25 |
Adriano Violante | XHEXP | Information | Fertigmeldung phase II cables SPB Optics Hutch D.02 and SPB laser hutch D.13 | ACTEMIUM has delivered the handover
document for the phase II cables installed
in D,02 and D.13. The beckhoff crates can |
|
185
|
27 Apr 2017, 17:41 |
Valerii Bondar | General | Information | Motion Loop is up | Dear all,
motion loop is up and all Karabo
devices in it are running. |
|
184
|
27 Apr 2017, 15:28 |
Tobias Haas | General | Information | Accelerator plans for the next 5 days | |
|
183
|
27 Apr 2017, 15:11 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | XTDs
Info: |
|
182
|
27 Apr 2017, 09:34 |
Tobias Freyermuth | XTD2 | Information | Update MOV loop | Hi all,
in order to integrate the CRL in |
|
181
|
27 Apr 2017, 07:11 |
Raúl Villanueva-Guerrero | XTD2 | Problem | XTD2 Differential Pumping completely OUT OF OPERATION! |
|
|
180
|
27 Apr 2017, 07:04 |
Raúl Villanueva-Guerrero | XTD2 | Problem | XTD2 Differential Pumping completely OUT OF OPERATION! | Dear all,
I just checked the Karabo Scene for |
|
179
|
26 Apr 2017, 19:21 |
Raúl Villanueva-Guerrero | XTD9 | Feedback | XTD9 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - SUCCESFUL | Dear all,
Finally the tests were run with the
expected results: Pressure thresholds for |
|
178
|
26 Apr 2017, 18:34 |
Jan Grünert | XTD9 | Problem | SA1-VAC loop down (only XTD9) and later restarted | Since around 17h30 all XTD9 VAC loop is
in error. It came back in karabo around 17h50.
XTD2 not affected. |
|