Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 363
Entry time: 18 Aug 2017, 11:23
|
Author: |
Tobias Haas |
Location: |
General |
Severity: |
Information |
Subject: |
Status and plans after SASE1/3 Readiness Meeting |
|
|
Software:
- CAS meets with SPB and FXE on a daily basis to fine tune progression towards user operation
- A list of required deliverables for user operation has been agreed between CAS and SPB/FXE (see slide 5 in presentation by H. Santos attached to these minutes)
- The list has been associated with Karabo releases and dates
- These dates and respective progress needs to be monitored continuously as the schedule is very tight
SPB
- AGIPD installation is progressing according to plan.
- Next steps are data taking and then the exchange of the detector modules by the consortium
- SmarACT stages in the sample chamber started working yesterday but it is not understood why they are working now while they were not working before
FXE
- Work continues on van Hamos integrations
- Next step is integration with the Tangerine laser
Tunnel Installations
- This week the focus was on SASE3 installation in XTD10
- The vacuum group closed almost all gaps
- A lot of cabling was completed
- Local tests together with AE are being carried out on the vacuum components
- MCP was delivered with too short bellows so this could not be connected
- XGM is connected on one side only
- The Diagnostics group brought PES into the tunnel
- 5/10 imagers are operational. 2 more are almost done
Laser
- Work is back on track after the cooling water incident 10 days ago
- AC controls are ok but the air flow is too high for laser operation
Electronics
- A lot of progress was made in the course of AGIPD integration in SPB (Chiller working, Gate Valve working. interlocks working and tested)
- A smaller effort was done for FXE (Some support for LPD and re-integration of van Hamos)
- Tests of the vacuum components in XTD10 are still ongoing and continue through Monday morning
- A new email with associated ticketing has been set up: ae-support@xfel.eu
|
|
|