Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 363     Entry time: 18 Aug 2017, 11:23
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and plans after SASE1/3 Readiness Meeting 

Software:

  • CAS meets with SPB and FXE on a daily basis to fine tune progression towards user operation
  • A list of required deliverables for user operation has been agreed between CAS and SPB/FXE (see slide 5 in presentation by H. Santos attached to these minutes)
  • The list has been associated with Karabo releases and dates
  • These dates and respective progress needs to be monitored continuously as the schedule is very tight

SPB

  • AGIPD installation is progressing according to plan. 
  • Next steps are data taking and then the exchange of the detector modules by the consortium
  • SmarACT stages in the sample chamber started working yesterday but it is not understood why they are working now while they were not working before

FXE

  • Work continues on van Hamos integrations
  • Next step is integration with the Tangerine laser

Tunnel Installations

  • This week the focus was on SASE3 installation in XTD10
  • The vacuum group closed almost all gaps
  • A lot of cabling was completed
  • Local tests together with AE are being carried out on the vacuum components
  • MCP was delivered with too short bellows so this could not be connected
  • XGM is connected on one side only
  • The Diagnostics group brought PES into the tunnel
  • 5/10 imagers are operational. 2 more are almost done

Laser

  • Work is back on track after the cooling water incident 10 days ago
  • AC controls are ok but the air flow is too high for laser operation

Electronics

  • A lot of progress was made in the course of AGIPD integration in SPB (Chiller working, Gate Valve working. interlocks working and tested)
  • A smaller effort was done for FXE (Some support for LPD and re-integration of van Hamos)
  • Tests of the vacuum components in XTD10 are still ongoing and continue through Monday morning
  • A new email with associated ticketing has been set up: ae-support@xfel.eu

 