SASE1 Status and SASE3 Readiness
 | 
|   Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  | 
Not logged in | 
  | 
   | 
| 
Message ID: 363
    Entry time: 18 Aug 2017, 11:23
 |  
| Author: | 
Tobias Haas  | 
 | Location: | 
General  | 
 | Severity: | 
Information  | 
 | Subject: | 
Status and plans after SASE1/3 Readiness Meeting  | 
 
  |  
 
 | 
Software: 
	- CAS meets with SPB and FXE on a daily basis to fine tune progression towards user operation
 
	- A list of required deliverables for user operation has been agreed between CAS and SPB/FXE (see slide 5 in presentation by H. Santos attached to these minutes)
 
	- The list has been associated with Karabo releases and dates
 
	- These dates and respective progress needs to be monitored continuously as the schedule is very tight
 
 
SPB 
	- AGIPD installation is progressing according to plan. 
 
	- Next steps are data taking and then the exchange of the detector modules by the consortium
 
	- SmarACT stages in the sample chamber started working yesterday but it is not understood why they are working now while they were not working before
 
 
FXE 
	- Work continues on van Hamos integrations
 
	- Next step is integration with the Tangerine laser
 
 
Tunnel Installations 
	- This week the focus was on SASE3 installation in XTD10
 
	- The vacuum group closed almost all gaps
 
	- A lot of cabling was completed
 
	- Local tests together with AE are being carried out on the vacuum components
 
	- MCP was delivered with too short bellows so this could not be connected
 
	- XGM is connected on one side only
 
	- The Diagnostics group brought PES into the tunnel
 
	- 5/10 imagers are operational. 2 more are almost done
 
 
Laser 
	- Work is back on track after the cooling water incident 10 days ago
 
	- AC controls are ok but the air flow is too high for laser operation
 
 
Electronics 
	- A lot of progress was made in the course of AGIPD integration in SPB (Chiller working, Gate Valve working. interlocks working and tested)
 
	- A smaller effort was done for FXE (Some support for LPD and re-integration of van Hamos)
 
	- Tests of the vacuum components in XTD10 are still ongoing and continue through Monday morning
 
	- A new email with associated ticketing has been set up: ae-support@xfel.eu
 
 
   | 
 |