Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 229     Entry time: 12 May 2017, 13:33
Author: Tobias Haas 
Location: General 
Severity: Information 
Subject: Status and plans after SASE1 Readiness Meeting 

Focus of meeting is on SASE1 Instruments, Laser and Detectors

SPB (B. Weinhausen)

  • All motors in the SPB tunnel loop have been commissioned except for one TECHNOSOFT motor where the updated driver was not yet available
  • Comment by P. Gessler:
    • The updated MC2 lib was deployed yesterday evening. Testing should be possible now
  • The second camera of the screen broke. Concern exists over possible overvoltage in the power that comes directly from the PLC
  • All encoders are working
  • The vacuum in the Optics hutch is closed
  • Info by A. Violante:
    • All cabling in D02/D03 is done
    • There are a few damaged connectors that prevent pushing in the modules. This should be fixed on Monday
    • Pins are swapped in one connector. Will be fixed locally
  • Comment by P. Gessler:
    • This week AE was busy with AGIPD and tunnels
    • Next week resources should be available to support start of commissioning loop 1 

FXE (A. Galler)

  • E2E tests are progressing 
  • A recent update of the Beckhoff firmware generated new problems with encoders
  • Info from T. Korsch:
    • The vacuum in the hutch is closed and has reached 5e-7 mb
    • There is a minor leak in one of the bellows
    • Compressed air is working to operate the gate valves
    • Vacuum gauges can be read out remotely
  • Attention should be paid to being able to read out detectors, e. g. diodes

Laser (D. Kane/M. Lederer)

  • Slides were provided in INDICO with a detailed account of the status. Only Key points are summarised here:
    • Hutch infrastructure is working in general and temperature stability is ok but laser group is lacking access to controlling the parameters, humidity is oscillating and smoke detectors are not connected
    • Pre-assembly of PP laser is 75% done
    • Beam delivery to instruments is on the list now
    • Synchronisation with optical system might not be available before October
    • Control are generally working and software has improved a lot but some stages cannot be controlled and Karabo appears still to have some resource leaks

Detectors (M. Kuster)

  • LPD is in E2E tests and AGIPD is still being integrated into the XFEL environment
  • This week it was possible to run the DAQ chain on LPD for the first time
  • All tests on LPD including data taking in the X-Ray chamber in HERA-S should be done by end June
  • Situation with AGIPD is more difficult as basic integration is still not complete

Discussion

  • Follow up on progress with instruments, laser and detectors will continue in S1R meeting from now on
  • The S1R dispatch meeting takes place on Mondays 09:00 in BKR and on Wednesday 09:30 in XHQ 
  • Groups that require help from AE and CAS and that need to coordinate with other activities should attend