Message ID: 6     Entry time: 31 Jan 2025, 06:28
Author: Jörg Hallmann 
Group: MID 
Subject: Shift summary 
  • Alignment of KB mirrors: focused beam H150-200nm x V300-350nm. Characterization of focused beam with wire scan.
  • Installed ePIX table and ePIX. Thorlabs server is not running, needs to be fixed by controls during the morning shift
  • Aligned rotation center of SSRY and put the beam into it. Moved alignment pin down by 10mm and put protecting cover on it.
  • Aligned DES spectrometer crystal (using YAG) to 9keV.
  • Checked CRL2 focusing with 9keV. Smallest is 9um (with bender adjust).
  • Alexey played with Mono further, second reflection not found. Problem found with actuator.
  • Tested FF data. Seems to be good.
  •  