Group Selection Page
HELP
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Operation
PSPO
XO
TS
Migrated2Zulip
|
OPERATION-2025
OPERATION-2024
OPERATION-2023
OPERATION-2022
OPERATION-2021
OPERATION-2020
OPERATION-2019
SASE1-2018
SASE1-2017
Experiment data
|
OPERATION-2025 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn |
Not logged in |
 |
|
Message ID: 6
Entry time: 31 Jan 2025, 06:28
|
Author: |
Jörg Hallmann |
Group: |
MID |
Subject: |
Shift summary |
|
|
- Alignment of KB mirrors: focused beam H150-200nm x V300-350nm. Characterization of focused beam with wire scan.
- Installed ePIX table and ePIX. Thorlabs server is not running, needs to be fixed by controls during the morning shift
- Aligned rotation center of SSRY and put the beam into it. Moved alignment pin down by 10mm and put protecting cover on it.
- Aligned DES spectrometer crystal (using YAG) to 9keV.
- Checked CRL2 focusing with 9keV. Smallest is 9um (with bender adjust).
- Alexey played with Mono further, second reflection not found. Problem found with actuator.
- Tested FF data. Seems to be good.
-
|