Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2024 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn  Not logged in ELOG logo
Message ID: 48     Entry time: 13 Mar 2024, 10:09
Author: Romain Letrun 
Group: SPB 
Subject: Status 

We checked the XTD2 attenuators following the intervention from XRO (compar ewith elog:37, before the intervention).

The wavefront shows similar distortions with the 75 and 150 um as earlier, which is not too surprising since the cracks are vertical.

Attachments 1-5: Beam on SPB_XTD9_SCR with XTD2 attenuator CVDs

Attachments 6-7: Beam on FEL imager with XTD2 75 and 150 um CVDs

Attachment 1: CVD_75um_2024-03-13_09-48-27.png  409 kB  | Hide | Hide all | Show all
CVD_75um_2024-03-13_09-48-27.png
Attachment 2: CVD_150um_2024-03-13_09-49-48.png  445 kB  | Hide | Hide all | Show all
CVD_150um_2024-03-13_09-49-48.png
Attachment 3: CVD_300um_2024-03-13_09-50-08.png  480 kB  | Hide | Hide all | Show all
CVD_300um_2024-03-13_09-50-08.png
Attachment 4: CVD_600um_2024-03-13_09-50-33.png  537 kB  | Hide | Hide all | Show all
CVD_600um_2024-03-13_09-50-33.png
Attachment 5: CVD_1200um_2024-03-13_09-51-41.png  468 kB  | Hide | Hide all | Show all
CVD_1200um_2024-03-13_09-51-41.png
Attachment 6: CVD_75um_2024-03-13_08-06-53.png  415 kB  | Show | Hide all | Show all
Attachment 7: CVD_150um_2024-03-13_08-06-07.png  383 kB  | Hide | Hide all | Show all
CVD_150um_2024-03-13_08-06-07.png
ELOG V3.1.4-7c3fd00