Message ID: 48     Entry time: 13 Mar 2024, 10:09
Author: Romain Letrun 
Group: SPB 
Subject: Status 

We checked the XTD2 attenuators following the intervention from XRO (compar ewith elog:37, before the intervention).

The wavefront shows similar distortions with the 75 and 150 um as earlier, which is not too surprising since the cracks are vertical.

Attachments 1-5: Beam on SPB_XTD9_SCR with XTD2 attenuator CVDs

Attachments 6-7: Beam on FEL imager with XTD2 75 and 150 um CVDs

Attachment 1: CVD_75um_2024-03-13_09-48-27.png  409 kB  | Show | Hide all | Show all
Attachment 2: CVD_150um_2024-03-13_09-49-48.png  445 kB  | Hide | Hide all | Show all
CVD_150um_2024-03-13_09-49-48.png
Attachment 3: CVD_300um_2024-03-13_09-50-08.png  480 kB  | Show | Hide all | Show all
Attachment 4: CVD_600um_2024-03-13_09-50-33.png  537 kB  | Show | Hide all | Show all
Attachment 5: CVD_1200um_2024-03-13_09-51-41.png  468 kB  | Show | Hide all | Show all
Attachment 6: CVD_75um_2024-03-13_08-06-53.png  415 kB  | Show | Hide all | Show all
Attachment 7: CVD_150um_2024-03-13_08-06-07.png  383 kB  | Show | Hide all | Show all
ELOG V3.1.4-7c3fd00