Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2024 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn  Not logged in ELOG logo
Message ID: 201     Entry time: 23 Nov 2024, 00:36
Author: Jan Gruenert 
Group: PRC 
Subject: Issue 

20h16: beam down in all beamlines due to a gun problem
20h50: x-ray beams are back
Shortly later additional 5 min down (20h55 - 21h00) for all beamlines, then the gun issue is solved.

After that, SA1 and SA3 are about back to same performance, but SA2 HXRSS is down from 130 uJ before to 100 uJ after the downtime.
Additionally, MID informs at 21h07 that no X-rays at all arrive to their hutch anymore. Investigation with PRC.

At 21h50, all issues are mostly settled, MID has beam, normal operation continues.
Further HXRSS tuning and preparation for limited range photon energy scanning will happen in the night.

Attachment 1: JG_2024-11-23_um_00.47.04.png  447 kB  | Hide | Hide all
JG_2024-11-23_um_00.47.04.png
ELOG V3.1.4-7c3fd00