Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2023 logbook, Contact: F.Wolff-Fabris, A.Galler, L.Samoylova, H.Sinn  Not logged in ELOG logo
Message ID: 85     Entry time: 17 Mar 2023, 01:48
Author: Johannes Moeller 
Group: MID 
Subject: Shift summary 

The intensity of the Seeding decreesed from 850 uJ to 550 uJ during the time between 20:00 and 02:00.

The Spectral purity also got worst, the beam in HIREX looks to have more SASE shoulders.

Between 18 and 20 we show a prossible transiant signal, PPL, of the lower branch. But a problem with the monochromator in the MID opt Hutch trigger the valve to close. After we where not able to see the signal possible effect of laser or X-ray inestabilities.

Problems with the liquidjet, the nozzel got clogged.

Started the aligment of the upper branch of SDL

Attachment 1: Screenshot_from_2023-03-17_01-44-53.png  77 kB  | Show | Show all
ELOG V3.1.4-7c3fd00