Message ID: 80     Entry time: 14 Mar 2023, 20:26
Author: Harald Sinn 
Group: PRC 
Subject: Issue 

SCS could only use two pulses, because the SXP imager was still in the beam and SXP shutter open. 

I removed the SXP imager, so SCS can now get the full beam. The SXP shutter is still open and SXP instrument contacted via email to find out, if the shutter is intentionally open. 

21:13: SXP confirmed that they will close the shutter tomorrow. The imager was just forgotten in the beam. 