Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
OPERATION-2025 OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2023 logbook, Contact: F.Wolff-Fabris, A.Galler, L.Samoylova, H.Sinn  Not logged in ELOG logo
Message ID: 80     Entry time: 14 Mar 2023, 20:26
Author: Harald Sinn 
Group: PRC 
Subject: Issue 

SCS could only use two pulses, because the SXP imager was still in the beam and SXP shutter open. 

I removed the SXP imager, so SCS can now get the full beam. The SXP shutter is still open and SXP instrument contacted via email to find out, if the shutter is intentionally open. 

21:13: SXP confirmed that they will close the shutter tomorrow. The imager was just forgotten in the beam. 