Message ID: 427     Entry time: 31 Oct 2023, 23:08
Author: Chan Kim 
Group: SPB 
Subject: Shift summary 

X-ray delivery

  • 19keV, 700-800uj

Optical laser delivery

  •  ns laser

Achievements/Observations

  • Vacuum pipe and He pipe for diamond outcoupling installed
  • Aligned beam to downstream
  • Saw the beam at tower position (Zyla camera)