Message ID: 42     Entry time: 19 Feb 2023, 00:34
Author: Richard Bean 
Group: SPB 
Subject: Shift summary 

X-ray delivery

  •  9.3 keV, 1-120 pulses,
  • good stabiltiy, lowish flux ~900uJ, but experimental requirements were met

Achievements/Observations

  • Finished doule slit measurements at micron beam
  • Alignment to direct beam
  • Sample position for the sand paper found
  • Some sand paper test speckle patterns measured

Issues

  • Alignment was a bit painful without the NKB and EHC cameras - switch to ZYLA at EHC made ALAS alignment much easier
  • diff pump does not transmit much of direct beam without interference and requries tight power slits (known limitation)

Instrument status

  • AGIPD HV off.
  • AGIPD gate valve closed and pinned.
  • Attenuators set to thickest diamond.
  • Vacuum valves closed.
  • EHU PSLIT closed around direct beam to approx 1.2 x 1.2 mm
  • sample moved up by 10mm so both rows accessible in direct beam
  • current 'focus' sample position is approx location of sandpaper from evening measurement (lower row, darkside), 10mm in +x moves out of beam

To do for next shift

- continue direct beam speckle measurements (See entry elog:138)
- quite a bit of scattter on AGIPD from direct beam and especially sandpaper samples.
- transmissions of at least ~1 % level are detector safe (no pixels in AGIPD medium gain)

 