Message ID: 389     Entry time: 14 Oct 2023, 09:48
Author: Frederik Wolff-Fabris 
Group: PRC 
Subject: Status 

Machine went down overnight (4AM and 6AM) and could not be properly restarted by BKR.

Ongoing tuning is proceeding with RC onsite since 6AM; Instruments are informed and in direct contact to BKR.

Status 09:45AM: SA1 ~3mJ; SA2: ~500uJ; SA3 being restarted

Status 11:10AM: Beam restored in all SASEs; SA1 delivery from 10AM; SA2 delivery from 11:10; SA3 delivery from 10:45