Message ID: 371     Entry time: 28 Sep 2023, 07:20
Author: Romain Letrun 
Group: SPB 
Subject: Shift summary 

Shift summary for 27.9.2023

X-ray delivery

  • 6.3 keV, 3-4 mJ/pulse, 1-352 pulses at 1.13 MHz

Optical laser delivery

  • PP laser, 1030 nm, 226 pulses at 1.1 MHz, delivered from 9:45 on and was stabilizing over the day
  • ns laser for rayleigh scattering, stabe delivery

Achievements/Observations

  • Aligned MKB trajectory and optimzed background
  • Scattering laser aligned with X-rays references and overlaped with particle beam
  • Few runs with sucrose while trying to optimize injection

Issues

  • PP laser was still drifting in energy and pointing, better stabilized towards the end of the shift
  • Difficulties with injection, tried sevral times and did not improve much
  • Slope in pulse energy along the pulse train, up to 40% change from first to last pulse
  • Significant background AGIPD after correcting beam trajectory