Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
OPERATION-2025 OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2023 logbook, Contact: F.Wolff-Fabris, A.Galler, L.Samoylova, H.Sinn  Not logged in ELOG logo
Message ID: 313     Entry time: 19 Aug 2023, 07:16
Author: Sergii, Manuel 
Group: SCS 
Subject: Noght shift sammary 18.08.2023 

Night shift summary on 18.03.2023

  1. Finished XAS series at 1.5 mJ/mm² for different delays
  2. Performed XAS at 6 mJ/mm²
  3. Tested tr-RIXS signal at 1mj/mm² with 29 different delays, signal too weak to continue
  4. Took 5 hours of tr-RIXS signal at 1.2 mj/mm² with 29 different delays

Problems:

  1. Something in the cryo line froze, cleaned the line by going into the hutch and moving the needle valve a bit. This only helped short-term, as it kept freezing after short time.
  2. Temperature sensor at the sample stopped working, started to work again during the heating
ELOG V3.1.4-7c3fd00