Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
OPERATION-2024
OPERATION-2023
OPERATION-2022
OPERATION-2021
OPERATION-2020
OPERATION-2019
SASE1-2018
SASE1-2017
Experiment data
OPERATION-2023 logbook, Contact: F.Wolff-Fabris, A.Galler, L.Samoylova, H.Sinn
Not logged in
List
|
Message ID:
288
Entry time:
05 Aug 2023, 08:20
Author:
Romain Letrun
Group:
SPB
Subject:
Shift summary
X-ray delivery
9.3 keV, 1-202 pulses at 1.13 MHz, 1.9-2.1 mJ.
Overall stable delivery.
L-IBFB could not be activated due to missing missing transfer matrix elements. Missing parameters entered by the expert who happened to be on shift this morning.
Optical laser delivery
800 nm, 50 fs, 564 kHz. Overlall stable delivery.
Achievements/Observations
Installation and alignment of fixed target sample.
Coarse timing of PP laser.
Found diffraction of sample.
Issues
Retracted CRL positions in MDL SA1_XTD2_CRL/MDL/CRL are not up-to-date and do not drive the CRLs to the "out" switch.
PP laser OXC synchronisation signal dropped out a couple of times. LbSync and LAS informed.