Message ID: 280     Entry time: 29 Jul 2023, 23:46
Author: Adam Round 
Group: SPB 
Subject: Shift end 

X-ray delivery

  • 12.4 keV, up tp 352 pulses but the intensity drop across the train was too dramatic to use. reasonably stable delivery with 202 pulses.

Optical laser delivery

  • none

Achievements/Observations

  • reestablished direct beam trajectory and verified instrument alignment
  • collected flat field calibration for AGIPD-1M for all high priority scenarios and some additional settings (see table copied in SPB commissioning or original AGIPD log)