Message ID: 266     Entry time: 20 Jul 2023, 18:20
Author: Antje Trapp 
Group: XRO 
Subject: Shift summary of SASE2 alignment 

Mirror pitch motors Ry were tested after scaling was changed to um.

Tx and Ry motor positions were calibrated to their measured physical positions.

ALL PREVIOUSLY SAVED SETTINGS FOR SASE2 MIRRORS ARE OBSOLETE!

New mirror positions for 9.3keV ; 2.2mrad ; B4C stripe are stored in MID-setpoints and HED setpoints

Please check the respective ELOG entries from July 20th