Message ID: 265     Entry time: 19 Jul 2023, 20:09
Author: Mikako Makita 
Group: XRO 
Subject: Shift summary: 19. July 

Summary of today's activity:

  • Beam handover ~ 3pm.
  • SA2 mirror set tp B4C.
  • SA2 Rough alignment to MID & HED @ ~ 2-2.5 mrad ==> img 1, 4, 5 & 6
  • SA2 HED-Preabsorber position check with x-ray (working) ==> img 2 &3
  • SA3 M6 mirror Switch check (seems to be working)
  • SA1 rough alignment to SPB (M1,M2) at 2 mrad ==>img 7&8
Attachment 1: MID-2-2mrad-2023-07-19_16-13-49.png  286 kB  Uploaded 19 Jul 2023, 21:57  | Show | Hide all | Show all
Attachment 2: HEDBeammonitor_YAG_2023-07-19_18-31-33.png  646 kB  Uploaded 19 Jul 2023, 21:58  | Hide | Hide all | Show all
HEDBeammonitor_YAG_2023-07-19_18-31-33.png
Attachment 3: HEDBeammonitor_diamond_2023-07-19_18-28-11.png  618 kB  Uploaded 19 Jul 2023, 21:58  | Hide | Hide all | Show all
HEDBeammonitor_diamond_2023-07-19_18-28-11.png
Attachment 4: 2023-07-19_16-43-19_beam_at_MID_2_2mrad.png  199 kB  Uploaded 19 Jul 2023, 21:59  | Hide | Hide all | Show all
2023-07-19_16-43-19_beam_at_MID_2_2mrad.png
Attachment 5: beam-on-mid-2023-07-19_16-09-45.png  288 kB  Uploaded 19 Jul 2023, 21:59  | Show | Hide all | Show all
Attachment 6: end-of-shift-beam-on-HED_2023-07-19_21-03-17.png  2.865 MB  Uploaded 19 Jul 2023, 22:04  | Show | Hide all | Show all
Attachment 7: SPB_aligned_2023-07-19_21-04-14.png  917 kB  Uploaded 19 Jul 2023, 22:19  | Show | Hide all | Show all
Attachment 8: SPB_mirrorAligned_2mrad_2023-07-19_21-15-54.png  63 kB  Uploaded 19 Jul 2023, 22:19  | Show | Hide all | Show all