  OPERATION-2023 logbook, Contact: F.Wolff-Fabris, A.Galler, L.Samoylova, H.Sinn  Not logged in ELOG logo
Message ID: 144     Entry time: 19 Apr 2023, 23:20
Author: Laurent Mercadier, Martin Teichmann 
Group: SCS 
Subject: shift summary day 2 UP3463 

Achievements

  • found larger beamstop
  • found center of pinhole and bender settings for beam size
  • checked jitter of beam on grating, looks like jittering is large, to be further investigated offline
  • checked that patterns are working for the night, to be continued by night crew

Problems

  • Major problems with scanner Y, as during the previous runs. Reset axis, Reset and adjust the target position to actual position + move to get out of error.
  • Problem with bunch pattern (see separate entry in Operations elog)
  •  

 